Project Timeline

4:30 to 5:45 p.m

Footings set-up (view photo)

5:45 to 6:00 p.m

Footings inspected
Stone added over plumbing

6:00 to 6:50 pm

Footings poured (view photo)

6:50 to 7:10 pm

Wall laid out on footings

7:10 to 8:45 pm

Walls Set (view photo)

8:45 to 10:00 pm

Wall squared and forms sprayed with release agent

10:53 to 11:15 pm

Wall poured (view photo)

11:15 to 11:30 pm

Footings Scraped
General cleaning done

11:30 p.m. to 1:00 am

Waited for walls to set and severe weather to pass

1:00 to 1:30 am

Wall stripped (view photo)

1:30 to 2:00 am

Started insulation application

2:05 to 2:25 am

Sought shelter from tornado spotted 10 miles to the west

2:25 to 3:30 am

Finished insulation
Stoned outside/inside of basement
Set steel beams and columns (view photo)

3:30 to 4:30 am

Horizon Foundation finishing system installed

4:30 am

Carpenters start first floor deck (view photo)

9:00 am

Foundation backfilled by builder