| Project Timeline | |
4:30 to 5:45 p.m |
Footings set-up (view photo) |
5:45 to 6:00 p.m |
Footings inspected |
6:00 to 6:50 pm |
Footings poured (view photo) |
6:50 to 7:10 pm |
Wall laid out on footings |
7:10 to 8:45 pm |
Walls Set (view photo) |
8:45 to 10:00 pm |
Wall squared and forms sprayed with release agent |
10:53 to 11:15 pm |
Wall poured (view photo) |
11:15 to 11:30 pm |
Footings Scraped |
11:30 p.m. to 1:00 am |
Waited for walls to set and severe weather to pass |
1:00 to 1:30 am |
Wall stripped (view photo) |
1:30 to 2:00 am |
Started insulation application |
2:05 to 2:25 am |
Sought shelter from tornado spotted 10 miles to the west |
2:25 to 3:30 am |
Finished insulation |
3:30 to 4:30 am |
Horizon Foundation finishing system installed |
4:30 am |
Carpenters start first floor deck (view photo) |
9:00 am |
Foundation backfilled by builder |